ebi espi PKNORLEN 2021-06-22 14:14

KOMISJA NADZORU FINANSOWEGO

Raport bieżący nr34/2021
Data sporządzenia: 2021-06-22
Skrócona nazwa emitenta
PKNORLEN
Temat
Umowa na budowę kompleksu olefin w Zakładzie Produkcyjnym w Płocku
Podstawa prawna
Art. 17 ust. 1 MAR - informacje poufne.
Treść raportu:
PKN ORLEN S.A. („Spółka”) informuje, że 22 czerwca 2021 roku podpisał umowę na budowę kompleksu instalacji Olefin III („Inwestycja”) w formule EPCC (Engineering, Procurement, Construction and Commissioning) dla zakresu ISBL ze spółkami Hyundai Engineering Co., Ltd. z siedzibą w Seulu oraz Técnicas Reunidas S.A. z siedzibą w Madrycie.

Inwestycja stanowi część Programu Rozwoju Petrochemii, który został ogłoszony przez Spółkę 12 czerwca 2018 roku. Całkowity koszt Inwestycji szacowany jest na około 13,5 mld PLN. Zakończenie fazy budowy Inwestycji planowane jest na 1 kwartał 2024 roku, a uruchomienie produkcyjne Kompleksu Olefin III na początek 2025 roku. Spółka szacuje, że realizacja inwestycji przyczyni się do wzrostu EBITDA o ok. 1 mld PLN rocznie.

Patrz także: raport bieżący nr 27/2021 z 24 maja 2021, nr 26/2021 z 24 maja 2021 roku oraz nr 69/2018 z 12 czerwca 2018 roku.

MESSAGE (ENGLISH VERSION)

Agreement for building of olefins unit complex in the Production Plant in Plock
Regulatory announcement no 34/2021 dated 22 June 2021

PKN ORLEN (“Company”) informs that on 22 June 2021 it signed the agreement for building of Olefins III unit complex (“Investment”) in EPCC formula (Engineering, Procurement, Construction and Commissioning) for ISBL with the companies: Hyundai Engineering Co., Ltd. headquartered in Seoul and Técnicas Reunidas S.A. headquartered in Madrid.

The Investment is a part of Petrochemical segment development program, announced by the Company on 12 June 2018. Total cost of the Investment is estimated at the level of ca. PLN 13,5 bn. Closing of the building phase of the investment is planned for the first quarter 2024 and start of production at the Olefins III Complex for the beginning of 2025. The Company estimates that realization of the investment would increase EBITDA by ca. PLN 1 bn annually.

See also: regulatory announcement no 27/2021 as of 24 May 2021, no 26/2021 as of 24 May 2021, no 69/2018 as of 12 June 2018.

POLSKI KONCERN NAFTOWY ORLEN SA
(pełna nazwa emitenta)
PKNORLENPaliwowy (pal)
(skrócona nazwa emitenta)(sektor wg. klasyfikacji GPW w W-wie)
09-411Płock
(kod pocztowy)(miejscowość)
Chemików7
(ulica)(numer)
24 256 81 8024 367 77 11
(telefon)(fax)
ir@orlen.plwww.orlen.pl
(e-mail)(www)
774 00 01 454610188201
(NIP)(REGON)
PODPISY OSÓB REPREZENTUJĄCYCH SPÓŁKĘ
DataImię i NazwiskoStanowisko/FunkcjaPodpis
2021-06-22Zbigniew LeszczyńskiCzłonek Zarządu
2021-06-22Iwona Waksmundzka-OlejniczakDyrektor Wykonawczy ds. Strategii i Innowacji oraz Relacji Inwestorskich
Czytaj więcej

Artykuły związane z ebi espi PKNORLEN 2021-06-22 14:14